Task deadlines and dependencies

These settings are in the Advanced section of the “Process task” dialog.

Set start/end date

Set start date

Defines when the task date is set:

Value When the date is set
On creation When the process is created.
Planned only Only if the task has the status “Planned”.
Not started If the task has the status “Planned” or “Open”.
Not completed If the task is not completed or cancelled.

The last three values are used when a task that depends on a parent or previous task is activated.

Start/end date offset

Date offset

The date from which the task's start/end date is calculated:

Value Reference date
None The date is not set.
Owner start The start of the object from which the task was created – for example the start of the engagement or the order. This date can be changed when the process is started.
Owner end The end of the object from which the task was created.
Parent task start The start of the parent task. Used in combination with the last three values of “Set start/end date”.
Parent task end The end of the parent task.
Previous task start The start of the previous task.
Previous task end The end of the previous task.

Days and minutes

How many days or minutes to add to the reference date.

Example: start = 3 days from Owner start, and the process was created from an engagement – the task starts 3 days after the date the engagement takes effect. End = −5 days from Owner end – the task ends 5 days before the end of the engagement.

Skip non-working days

When selected, the non-working days from the main work calendar are skipped when adding the days and minutes.

Link to a task

When the task is activated relative to the parent or previous task:

Value When the task is activated
Finish-to-start After the parent/previous task finishes.
Start-to-start After the parent/previous task starts.
Finish-to-finish Not currently used for activation.
Start-to-finish Not currently used for activation.